13 Jul 2011

Day 5 - Back on Track




Although the wall got underway yesterday, that was little more than a training exercise and the real work began today. The boys had to complete at least three lines of bricks all the way around, preferably far more, if we were to stand any chance of completing the project on time. Progress initially was slow as boys got to grips with working with the uneven bricks and extraordinarily almost all of them could not understand that the bricks had to be laid in an interlocking pattern. They were focusing on making sure they were level and straight, but ignored how they interacted with all the surrounding bricks. A generation ago it was unthinkable that any boy who had grown up with good old fashioned Lego bricks could make such an error but it would seem that most of the boys had never had the pleasure of working with such simple generic bricks; Lego nowadays is small, fiddly and custom built for each specific model. With hindsight it would have been fantastic to have a set of such Lego to show the boys exactly what was required. As a result of this oversight and the modern advances in injection moulding technology the first three layers were a sight for sore eyes; there was no discernable pattern and mortar all over the place. By the end of the day though most of the boys had realised the error of their ways and hopefully this become apparent tomorrow.

Meanwhile, on the other side of the courtyard a group of boys were helping two local wood craftsmen to construct the trusses to support the roof. There are 13 of these to be made and it was expected that these would take three days to construct. Progress was slow initially as they worked out the exact sizes that would be required. Once the first one was constructed though, they used it as a template and built all the subsequent ones on top of it. This sped up hugely and the boys were able to get involved, selecting wood, sawing and carrying. Unfortunately it quickly became clear that there were some parts of this job that had to be completed by skilled labour as they involved an extremely sharp carving tool. Nevertheless, the boys were very helpful, by the end of the day second guessing the requirements of the craftsmen and enabling the completion of 6 trusses. There are only 7 to go and these should be completed tomorrow; a day ahead of schedule and a couple of days before they are needed.

Apologies for the delay in posting this – the power up on the mountain has been going on and off incessantly and although we have a huge backup generator the next link in the internet chain doesn’t.

12 Jul 2011

Day 4 - Going Up!

The day started 30 minutes earlier again today as the boys attempted to make best use of the daylight, requiring a 7.30am departure.  Work began immediately that everyone arrived on site, with the various teams of boys dividing themselves up quickly and getting on with the tasks at hand. Everything appeared to be going very smoothly and there was a push to complete the floor by lunchtime; this was until the pile of gravel rapidly disappeared until finally the concreting had to stop at  9.30am. Another truckload was already on its way, bringing the total so far to 28 tonnes, but that didn’t for another hour, at which time the site went into overdrive again.

Whilst this final push was taking place a small team was taken to one side to be trained in the mysterious art of brick laying. This involved in the first instance installing to vertical guides to work from and then stringing a horizontal line across to ensure that the bricks remained level. The boys were quick learners and within minutes were laying the first line of bricks along the back wall of the building, nearest the chapel. The lunch break had to be delayed slightly until one of the concrete sections was completed, but this meant that four had been completed in the morning, a mammoth task, leaving only one more to go (gravel was once again in short supply though as the 7 tonnes delivered that morning had already been exhausted).

Fortunately it had been possible to arrange for the farm hands to collect some gravel over lunch and the team were able to lay that final slab of concrete upon their return. The boys mixing the concrete at the end were definitely showing signs of fatigue but everyone could congratulate themselves on a job well done; it was truly an extraordinary feat. I think it’s safe to say that many of the boys would gladly never mix another batch of concrete in their lives, although at least now they would know exactly what to do.

The brick layers made steady progress throughout the afternoon with four layers of the end completed by the end of the day. Now that the concrete laying has been completed the rest of the team can turn their hands to brick laying too so the building should really start to take shape over the next couple of days.

11 Jul 2011

Day 3 - Pouring the Floor - Part 2


Sequels rarely live up to their predecessor but not in the case.

The day began wonderfully with our first glimpse of sunshine since arriving in Africa, and continued to warm us throughout the day. Everyone know the task ahead, but no-one quite knew how much progress could be made in the relatively few hours of daylight available. Nevertheless the boys split up into their teams and got to work immediately. There is so much to do at the moment that every boy had a specific job to do and worked hard at it all day. For most this meant mixing concrete for 6 hours. At about 11am another 7 tonnes of gravel arrived, but not on a lorry that could tip it out, so one group had to spend about  an hour shovelling it all off. While this was going on another group left on another lorry to collect a few tonnes of sand; it had to be shovelled on and shovelled off again. Fortunately in both these, and every other task, help was on hand from the vast number of local people who are helping; some of these are paid labourers, but most are children who live nearby and no doubt go to the school. You may see from the pictures that in addition to this there is an audience of a few dozen children who have watched us throughout the project thus far.

By the time the boys broke for lunch they had completed 6 of the 13 concrete slabs that were required and planned to do two more upon their return.

You may remember that I spoke ill of the lunch yesterday; I’m pleased to report that we were given crisps today – thank you chef!

After  lunch it was all hands to the pumps again and the final two slabs were poured in record time; about twice as fast as the day before.  Tomorrow we have the simpler task of filling in all the alternate slabs to complete it; meanwhile the end walls will start to take shape.

10 Jul 2011

Day 2 - Pouring the Floor - Part 1

Arriving on site at 9am this morning the scene at the school had changed greatly overnight. The promised labourers from a nearby farm (The farmers, Michael and Zoe, have been a huge help to us; they suggested the project originally and are providing daily support to us throughout our time here) were ready and waiting as were two tankers of water and a trailer full of spades, buckets , wheelbarrows and other assorted equipment. Within minutes all the boys were busied; some emptying the trailer whilst others started to mix the concrete for the foundations.
Unfortunately the floor wasn’t quite ready to pour as it needed one more layer of bricks around the outside to provide a level to fill to. Once the trailer was emptied it went off to collect the bricks for this task. In the meantime the pile of dry concrete mix was growing ever larger and the constant threat of rain eventually led us to cover it with tarpaulin.

The bricks arrived soon enough and the boys helped the local workforce to lay the one layer that we needed, completing the job before lunch. The first section of shuttering was also completed and would be ready and waiting to be poured as soon as we returned from lunch at the farm.

Although I digress I should mention that the breakfast and supper at the hotel have so far been varied, abundant and very tasteful – the packed lunch less so, consisting of a sandwich of indeterminate, though tasty, filling, some cold chips and an apple. After some discussion it was decided that the cold chips were probably supposed to be ‘crisps’, something being lost in translation. Fingers are crossed for tomorrow.

After lunch everyone went into overdrive as as much concrete as possible needed to be poured in the three remaining hours of daylight. Concrete was being mixed as fast as it possibly could be with teams not only using the mixer but also making up batches on the ground. Nevertheless in the end the area covered was about one sixth of the total floor area. The workmen are arriving on site at 6am tomorrow to get a head start and the boys should be joining them at 8am. We will certainly get most of the floor completed tomorrow, but whether we can finish it as hoped remains to be seen.

Everything was cleaned up and everyone was off site by 4.40pm. Although quite early, the light was already fading and we only just made it back to hotel before darkness fell. The cloud had lifted significantly though so we could all appreciate the drive up the mountain this time. Tired, dirty, but satisfied at the end of a tough day, the boys raced to the showers, not quite knowing how much hot water might be available.

9 Jul 2011

Day 1 - Arrival (Eventually!)

All the pieces, or should I say people, finally fell into place at Heathrow. Anxiety was growing at the prospect of not having a full complement by the time the flight boarded (I should add that this was entirely due to the weather in Edinburgh, and not any individual’s fault!). Eventually the last boy from Scotland joined us at the check in desk just as we persuaded the extremely helpful SAA staff to carry our excess baggage at no extra cost. The excess baggage was not entirely normal, consisting mostly of tools from the school workshop and safety equipment courtesy of Mr Cherry. 
The journey from this point on was very smooth, and the two extras joined us at Johannesburg  airport as expected.  Things only started to get complicated on the final descent into Blantyre. The landing gear had been lowered and the airspeed had dropped and we were expecting to land in a few minutes. The cloud was quite low though and at what appeared to be the last minute (but wasn’t!) the engines roared and we lifted up again. Mr Smith and I shared a knowing glance and knew that something had just gone wrong. A couple of minutes passed before the captain announced that the Instrument Landing System at the airport was not working and due to the low cloud it was impossible to land. As I write this we are sitting on the tarmac at Lilongwe, waiting for the weather to clear or the I.L.S. to be repaired at Blantyre. (I don’t want to worry any of you by posting this story without a happy ending, even though I can get a 5 minute free trial of the internet connection at Lilongwe airport.)

Eventually the cloud cover lifted at Blantyre and the message got through to us on the ground; it seems that the telephone communications between the two airports were not very reliable. We all applauded upon hearing the news and then again when we finally touched down in Blantyre three hours late. The journey to the hotel, via the school, was very interesting and gave the boys a very vivid introduction as to what daily life is like for the people in this part of Africa. Arriving at the school just before dark there was just time to say hello and then head off to the hotel before darkness set in. The final climb to the hotel was up into the cloud cover we had been trying to avoid all day; visibility was challenging but the drivers knew the road and everyone arrived at the hotel safely for supper and an briefing about the next day’s plan of works.

15 Jun 2011

Project Maps

The first map shows whereabouts in Africa the project will be taking place. (Each red square is detailed in the mpa below.)

















This third map shows exactly where in Malawi the different elements of the trip will be taking place. To give some sense of the scale of this map Lake Chilwa is about 20 miles across.

8 Jun 2011

Foundations


The foundations are being dug ahead of our arrival on July 9th. Please have a look at the photo gallery to see the progress that has been made.






This gives some idea of the scale of this project. The footprint outlined here will be turned into a partially enclosed classroom/assembly hall in just 10 days.